Castle Wharf, Nottingham

SFS delivered firestopping works at Castle Wharf, Nottingham in line with an approved Project Pack, achieving full fire safety compliance with complete QA records.

Firestopping

Project overview

Structural Fireproofing Systems completed firestopping refurbishment works within an existing, unoccupied residential development to improve compartmentation and support ongoing fire safety compliance. All works were undertaken strictly in accordance with an approved Structural Fireproofing Systems Ltd (SFS) Project Pack.

The Challenge

Working within a specification on an unoccupied residential development, the priority was to adhere strictly to the approved details with full documentation of every installation.

     

  • The scope of works was clearly defined and limited to approved firestopping details only.
  •  

  • Full traceability and certification were required to support compliance and future building management.
Our Solution

To deliver all solutions according to the guildlines, with specialist operatives ensuring every installation was consistent, certified, and fully accountable.

  • SFS delivered the works strictly in line with a pre-approved Project Pack, developed prior to commencement and agreed with the client team.
  • All firestopping installations followed tested, manufacturer-approved systems detailed within the Project Pack, with no deviation on site.
  • Works were carried out by FIRAS-accredited operatives, experienced in refurbishment environments.
  • Installations were recorded with photographic QA evidence and digitally logged, providing a clear and auditable record of compliance.
The Results

The refurbishment was completed diligently, in alignment with the specifications and with complete documentation, supporting the building’s compliance requirements.

  • Firestopping refurbishment works delivered fully in accordance with the approved Project Pack.
  • Programme delivered efficiently within an unoccupied refurbishment environment.
  • Full QA records and third-party certification issued, contributing to the building’s Golden Thread of compliance

Need help with your firestopping project?

Learn how we can help deliver safely and on time – speak to our team about your project.